How we count schedules, and why we add the buffer where we do

12 November 2026 · 6 min read · by the Wavo Post team

A date on a post schedule is a promise made by several people at once. We count it bottom-up and add slack in a few specific places, not as a flat percentage.

Rules of thumb

Example: a 30-second commercial

Shoot: two days. Dailies the morning after each. Edit: three days. Two review rounds: four days. Grade: half a day. Sound check and delivery in six versions: three days. Total: about 13 working days from the end of the shoot, if notes come back on time.

Example: a 52-minute documentary

Assembly: about five weeks for 40 hours of footage. Two cut reviews: three weeks including client time. Fine cut and lock: two weeks. Conform and grade: five days. Mix and sound check: one week. About 13 weeks overall.

Where we put slack

  1. Before the first review: unknown footage always needs more sorting than expected.
  2. After picture lock: late changes to graphics and titles are the most common reason for a re-conform.
  3. Before delivery: a rejected technical check costs a day, and we would rather have that day free.

Where estimates slip

Almost never in the work itself. They slip while waiting: for notes, for music licences, for a decision on a title card. We put those waiting periods on the schedule as separate lines, with a name next to each, so that everyone can see whose turn it is.

Wavo Post

Dailies, review and conform for documentaries, series and commercials.

hello@wavostudio.com

StudioServicesProjectsRatesAboutCareersJournal
ClientsSign inSupportSystem statusContact
LegalPrivacyTermsCookies

© 2026 Wavo Post. Access to review rooms is by invitation.